Home > Projects > Real Estate Projects > Residential > Baishnabghata Patuli Township > Status Reports

: PROJECTS : New Area Development   :

STATUS REPORT :: AD SECTOR , KMDA


BAISHNABGHATA - PATULI HOUSING SCHEME
Phase - I (Housing)
Estimated Cost : Rs. 1763.02 Lakh. ( Civil )
Major Components

Construction of 408 nos. of Housing flats of different sizes from 550 sq. ft. to 1100 sq. ft.(approx)

Date of Commencement January ,1996.
Present Physical Status 408 No. Flats completed.
Date of Completion December , 2004.
Expenditure upto January, 2005 Rs. 1388.36 Lakh.
Remarks Flats are almost allotted.
 
Phase - II ( Housing )
Estimated Cost Rs.1,089.00 lakh. ( Civil )
Major Components Construction of 210 nos residential
flats of Different sizes
Economy type 160
Super Deluxe 50( 640sq ft to 1300 sq ft.)
Date of commencement March , 2005
Expenditure up to January , 2005 Rs. 879.64 Lakh
Remarks Out of 210 beneficiaries-160 nos. have already been selected Offloading for balance 50 No. flats had been made recently.

Phase - III ( Housing )
Estimated Cost : Rs. 1702.76 Lakh. ( Civil )
Major Components of the Scheme : Construction of 277 Nos. Residential Flats of different sizes. Economy Type =40, Super Deluxe=187, Delux = 50 ( 540 Sq.ft. to 1100 Sq.ft. )
Date of Commencement January , 2002 .
Expenditure upto January ,2006 Rs. 568.61 Lakh.
   
Phase - IV ( Housing )
Estimated Cost Rs. 2470.53 Lakh. ( Civil )
Major Components of the Scheme : Construction of 342 Nos of Residential Flats of Different Sizes super Deluxe=296,Deluxe=46 ( 702 Sq.ft. to 1340 Sq.ft. )
Date of Commencemen February , 2003
Present Physical Status : Works for 294 no. Flats have already been taken up in 8 No.Blocks whereas 4 No. Blocks are expected to be completed on December , 2005 ; Works for 32 No. flats to be taken up shortly.
Date of Completion : June , 2006.
Expenditure upto January , 2005 : Rs. 638.89 Lakh.
Remarks : Off-loading for 16 no. flats had been made recently.